Shale Remodeling uses time and materials pricing. It is setting prices for next year using the following information: Labor rate, including fringe benefits $ 86 per hour Annual labor hours 3,100 hours Annual materials purchase $ 1,316,250 Materials purchasing, handling, and storage $ 315,900 Overhead for depreciation, taxes, insurance, etc. $ 780,000 Target profit margin for both labor and materials 25 % What should Shale set as the materials markup per dollar of materials used

Respuesta :

Answer:

49%

Explanation:

Material mark up per dollar of material used = Target profit + Percentage of material purchasing , handling and storage

Material mark up per dollar of material used = 25% + (315,900/1,316,250 *100)

Material mark up per dollar of material used = 25% + 24%

Material mark up per dollar of material used = 49%