It takes 4000 persons hours to complete a project. How many weeks will it take a team of 5 people to complete the project if each person works 8 hours a day, 5 days a week?

Respuesta :

4000/5 people = 800 hours per person.
5x8 = 40 hours a week per person
40x5 people = 200 hours a week with all 5 people working.
800/200 = 4 weeks
The answer is 4 weeks

Otras preguntas